Dedicated Pavement Rehabilitation Crew
The City of Portola's Public Works team commenced work during the summer of 2025 to rehabilitate pavement in our city. We have targeted locations for rehabilitation based on a variety of factors including condition, traffic flow, and overall impact to the community.
This effort is funded through allocations from California Senate Bill 1 (the Road Repair and Accountability Act of 2017) and all of the work thus far as been performed by City staff.
October 2025 Progress:
Location: Gulling Street Bridge- Middle Section
Work Completed: Northbound and Southbound Lanes


Septemeber 2025 Progress:
Location: South Gulling Street and Commercial Street
Work Completed: Northbound and Southbound Lanes


July 2025 Progress:
Location: Gulling Street near the intersection of Gulling Street and East Riverside Ave
Work Completed: Southbound lane and crosswalks painted


June 2025 Progress:
Location: Gulling Street near the intersection of Gulling Street and East Riverside Ave:
Work Completed: Northbound lane